Should I stop the job on my floating extension?
All manner of questions and solutions to problems and issues surrounding the subject of brickwork, blockwork and stonework

2 posts   •   Page 1 of 1
MattM
Labourer
Labourer
Posts: 1
Joined: Wed Sep 15, 2021 7:11 am

Should I stop the job on my floating extension?

by MattM » Wed Sep 15, 2021 7:32 am

I'm having a floating extension built. The builders have put up the columns and started putting up the supporting wall. I came home to see this was the work they had done.

The gaps between the brick & mortar & the rubble is making me very nervous. I'm going to speak to them today but wanted to get some advice from people more knowledgable than myself.
Attachments
P3380121_1.jpg
P3380126_1.jpg
P3380128_1.jpg
P3380123.jpg

stoneyboy
Project Manager
Project Manager
Posts: 6534
Joined: Wed Dec 10, 2008 6:44 pm

Re: Should I stop the job on my floating extension?

by stoneyboy » Thu Sep 16, 2021 9:29 pm

Hi mattm
Not sure what is being built but suggest you get the building inspector in before is goes too much further.
Regards S

2 posts   •   Page 1 of 1
It is currently Sat Nov 23, 2024 10:20 am