Replastering 1 meter up wall after Damp Course
Ask your questions and find answers on many subjects relating to plastering and dry lining

3 posts   •   Page 1 of 1
chips
Labourer
Labourer
Posts: 4
Joined: Wed Feb 03, 2010 4:22 pm

Replastering 1 meter up wall after Damp Course

by chips » Tue Mar 23, 2010 12:22 pm

I've removed render and skim coat aprox 1 meter up the wall where damp is coming through wall. External bridge of damp course removed, additional Damp Course injection done, inside re-rendered with sand and cement. What's left is the skim coat.

My question is whether i must skim right up the wall or if i can blend the skim coat into the wall above the newly rendered area. Cheers

stoneyboy
Project Manager
Project Manager
Posts: 6536
Joined: Wed Dec 10, 2008 6:44 pm

by stoneyboy » Tue Mar 23, 2010 10:52 pm

chips,
"can blend the skim coat into the wall above the newly rendered area" YES

Dan the man
Ganger
Ganger
Posts: 109
Joined: Tue Sep 15, 2009 10:47 pm

by Dan the man » Wed Mar 24, 2010 1:54 pm

Depends on how good you are at skimming lol
If the wall is going to be painted afterwards then chances are you will see a slight join. If its your own house then I would skim the whole wall.