Concrete Slab with footings advice needed please

Posted: Tue Nov 22, 2011 6:45 pm
by dunny1234
I'm preparing ground for concrete slab. I've now dug my slab area (10m x 6m), and 225mm deep footings around the perimeter and up the centre as recommended by structural engineer (where timber frame panels will be).

I've started to lay my sub-base (803), next will be a layer of sand. After this i plan to construct my formwork around the perimeter, lay my DPM, place steel mesh and then pour concrete.

I think i'm doing this the correct way? Any advice would be gratefully received? Really want it to be right before the scary pour of concrete

Thanks in advance

Re: Concrete Slab with footings advice needed please

Posted: Wed Nov 23, 2011 7:27 am
by welsh brickie
you will have to contact the building control officer before you proceed to pour the concrete.He is the best person to advise you

Re: Concrete Slab with footings advice needed please

Posted: Tue Feb 14, 2012 10:22 am
by bob2012
If you’re having problems calculating how much concrete you need, Google "tarmac.co.uk/concretecalculator"
It works quite good on my moby as well.