This is a work premises related question.
We have a unit which runs up to 22Amp and is tested for at least 6 hours at a time. We need to wire to the unit properly as we are using the standard 16A ring main and things are getting a little warm...
We have a consumer unit with 100 amp main trip and lots of different trips for different sections of the building.
I was looking at changing one of the unused 16A trips and put a 32A in it place. Then run wires 20m down the building (in conduit) to where the unit is tested then terminated to a 32A blue Euro connector attached to the wall.
Can this be done the way I described?
I also need to know what circuit type do I need run:- Radial or spur?
What gauge of wire is recommended
Do I change from the standard trip to the new RCD type
Any pointers would be very helpful
:)