Building over a stream

Posted: Sun Aug 14, 2011 3:49 pm
by sd75
Hi everyone
We are looking into taking down a conservatory and replacing with an extension but our property has a stream cutting across the back garden and underneath part of the bungalow. This continues under our road and beyond. I doubt we would be allowed to close it up / block off our section of the stream. Can anyone advise us as to how difficult / additional cost this would incur with laying foundations ? The road has no history of flooding and there are no visible signs of subsidence, leaks, cracks, damp etc.
Thanks
Scott

Building over a stream

Posted: Mon Aug 15, 2011 10:28 pm
by xavi99
Scott

Foundations need to be excavated down to suitable firm ground. The joy of excavations is that you never know when you will reach good ground until you do the work unless you have dug a few trial holes.

It all depends on how deep. If you are into silty river bed then you may need piles but if you are either side of the stream then a traditional foundation with beams bridging over may well be good enough.

I would suggest consulting a structural engineer at an early stage. It is a difficult one to assess on the basis of a post but at least you are aware of the issue.

Good luck,

99

stream

Posted: Wed Aug 17, 2011 4:24 pm
by welsh brickie
you need to lay a large diameter pipe,to allow the water through and under the consevatory,excavate your foundations as normal but where the foundations meet the pipe encase the pipe in concrete.Also at the start of the pipe you need to create a concrete wall around and under the pipe to divert all the water into it.
Remember this is just a guide all this will have to be passed by the building inspector

Posted: Thu Aug 18, 2011 9:08 pm
by sd75
Thankyou both, appreciate it