Tile first or fit fixtures?

Posted: Tue Aug 23, 2011 1:14 pm
by Rastanking
Hi everyone,

I intend to fit a shower curtail rail around my bath and retile but which is the generally accepted sequence.

Is it to fit the fixtures and then tile or tile first and then fit the fixtures by drlling through the tiles?

Any help would be appreciated.

Re: Tile first or fit fixtures?

Posted: Tue Aug 23, 2011 11:02 pm
by jemball
Normally tile then fixtures. Otherwise you may have some impossible tile cutting to do and it will look messy.

Re: Tile first or fit fixtures?

Posted: Wed Aug 24, 2011 5:04 pm
by Rastanking
Thanks for the information, much appreciated.