Plumbing,Inspection chambers,sewrage

by khan71 » Tue May 19, 2009 2:17 pm

Hi I have a problem as I building a double extention on my driveway but main sewarage going inderneath which is roughly 10feet deep If i to have easiest way I can connect existing toilet and new one with the existing pipe work making a internal chamber under floor without digging up or have a new inspection chamber on back of newbuilt extention and run through a new pipe line under the building into main big chamber in front of house.Please any advice.
Regards

stoneyboy
Project Manager
Project Manager
Posts: 6536
Joined: Wed Dec 10, 2008 6:44 pm

by stoneyboy » Tue May 19, 2009 9:30 pm

khan71,
You must talk to your local building inspector and get their agreement.