Bridging the gap Between two Foundation Walls
Drainage pipes, concrete, footings and foundations. Post your questions and find answers here

timmywo
Labourer
Labourer
Posts: 3
Joined: Thu Sep 21, 2017 8:08 am

Bridging the gap Between two Foundation Walls

by timmywo » Thu Sep 21, 2017 8:38 am

Hello all,

I am in the process of completing an extension next to an existing building. The new extension was built 80cm from the existing building due to digger access. I now need to fill in this gap.

Background: Extension approx 8x7m, slope site, finishing foundation walls and preparing for fill then Concrete slab pour. The new structure is a reclaimed wood beam house. The extension has concreate footer 50x35cm and CMU blocks filled with cement. The old structure is concrete trench pour.
Location south Poland, winter -30c. The 80cm gap between buildings will not be a supporting wall.

Option 1:
Digg down below the frost line, put up shuttering and fill with cement to the desired level.

Option 2:
As above, but drill and epoxy in some horizontal rebar into both foundations.

As this gap is so small, I'm guessing Option 2 may be best as this wall with the rebar could even float above the ground, maybe I do not need to dig below frost line? If that is the case maybe best to rebar into the new foundation only.

Keen for feedback and suggestions, thank you all!

-Tim

It is currently Mon Dec 23, 2024 7:58 am