Fixing Quarry Tiles and Bringing Them up to Desired Height
Help, advice, information, answers and tips on all types of flooring from laminate and carpet to timber and vinyl

3 posts   •   Page 1 of 1
Coltheref
Labourer
Labourer
Posts: 2
Joined: Tue Apr 28, 2020 4:45 pm

Fixing Quarry Tiles and Bringing Them up to Desired Height

by Coltheref » Tue Apr 28, 2020 5:11 pm

I'm adding some 6mm thick quarry tiles to an area of low footfall floor that has been stripped and screeded with sand and cement. I need to bring the level up to the existing quarry tiles which are 15mm thick, so there is a depth of 9mm to make up. Can I do that with adhesive, or should I add another depth of screed say 4-5mm?
Attachments
Approx. 1.5 sqm to cover
Approx. 1.5 sqm to cover

stoneyboy
Project Manager
Project Manager
Posts: 6538
Joined: Wed Dec 10, 2008 6:44 pm

Re: Fixing Quarry Tiles and Bringing Them up to Desired Height

by stoneyboy » Wed Apr 29, 2020 10:53 pm

Hi coltheref
Suggest you use self-levelling compound preferably one including latex - an ordinary sand/cement mix is not very good for the thickness you have..
Regards S

Coltheref
Labourer
Labourer
Posts: 2
Joined: Tue Apr 28, 2020 4:45 pm

Re: Fixing Quarry Tiles and Bringing Them up to Desired Height

by Coltheref » Thu Apr 30, 2020 8:00 am

Many thanks, that's good advice, appreciate the feedback.