by thedoctor »
Sat Mar 31, 2007 8:37 am
Yes. Dig down to the underside of the pipe for 400mm either side of it. You will then have a thickening of the foundation in these areas. See our foundations project on the website which ( using a stepped foundation as an example) demonstrates this thickening. Lay the blocks up to the pipe either side and place a lintel over with at least 400mm bearing either side of the pipe. This will sread the load of the blockwork above the pipe all the way back to the main foundation.