by bobtb007 »
Tue Feb 28, 2012 4:51 pm
HI Rob
With your current system your biggest problem will be to maintain the static head in the system.
I take it you will be putting some form of hot and cold water and then also some heating via radiators in there
The header tank for the heating system will need to be at least 0,5m above the highest point that is served in the loft i.e. 0.5m above the highest radiator.
The cold water storage tank will need to be 0.5m above the highest hot water pipe (shower head?)
It will need some careful thinking to be sure and it all depends on what you want to do, you also will need to pay close attention to the storage capacity of the cold water storage tank(s?).
Huh, power showers, now that depends on what you mean, do you have a shower that is gravity served and has a pump on it or do you have a shower that has an integral pump but it is still served with hot and cold water?
Combi boilers dont need pumps on them to feed showers as they use mains pressure
I prob need some more details to make sense of what you are trying to do
Russ