socket height
Ask questions and find answers to many subjects relating to electrics and electrical work

8 posts   •   Page 1 of 1
daveh123
Labourer
Labourer
Posts: 3
Joined: Sun Sep 16, 2007 10:37 am

socket height

by daveh123 » Sun Sep 16, 2007 10:41 am

The regs state socket height as between 450 - 1200mm is this set in stone or is there a certain amount of flexibility? As 450mm is nearly half way up the wall (slight exaggeration!!!!).

kbrownie
Project Manager
Project Manager
Posts: 1995
Joined: Mon Mar 05, 2007 9:36 pm

by kbrownie » Sun Sep 16, 2007 5:43 pm

HI daveh123
These are the regs and I agree with you does seem a bit excessive, but should be complied too, it seems daft not too, if the job is being done anyway. Last thing you want is jobsworth telling you to remove and fit correctly The main reason for this regulation is for easy use by wheelchair bound people.

Kind Regards
KB

sparx
Project Manager
Project Manager
Posts: 2166
Joined: Wed Mar 21, 2007 8:33 pm
Location: The fifth continent.

by sparx » Sun Sep 16, 2007 8:11 pm

Hi, don't forget this only applies to new build & 'substantial refurbishment'
if only adding to/modifying original then need only be 'No worse than previous',
[This requirement is from Disability Discrimination Act not electrical regs.]

uajamesh
Labourer
Labourer
Posts: 2
Joined: Thu Dec 20, 2007 6:02 pm

by uajamesh » Thu Dec 20, 2007 6:51 pm

sorry to jump in on this post, but sparx, do you know if a loft conversion qualifies as a "new build or a substantial refurbishment"?
Many thanks

sparx
Project Manager
Project Manager
Posts: 2166
Joined: Wed Mar 21, 2007 8:33 pm
Location: The fifth continent.

by sparx » Mon Dec 31, 2007 7:58 pm

Loft conversions are considered as new work locally but it seems to vary with each LABC, but as someone too disabled to reach standard height sockets unlikely to be upstairs anyway!
phone LABC they are usually quite helpful, (suprisingly for gov. dpt!)
regards SPARX

ericmark

by ericmark » Mon Dec 31, 2007 10:27 pm

I seem to remember something about rooms to which visitors could be expected to use. But again kbrownie is right jobsworth is a problem and even if you don't need to mount at the recommended hight it saves the problems with inspectors later.

juli-juan
Apprentice
Apprentice
Posts: 12
Joined: Wed Jan 02, 2008 8:16 pm

by juli-juan » Wed Jan 02, 2008 9:10 pm

if its a rewire u can keep all the same as before if u are not adding any more new points all new points must be 450mm or below 1200mm all to do with DDA

uajamesh
Labourer
Labourer
Posts: 2
Joined: Thu Dec 20, 2007 6:02 pm

by uajamesh » Thu Jan 03, 2008 3:37 pm

Hello all,

Many thanks for your assistance, particularly sparx. I'll be contacting the LABC guys as soon as i finish this reply...

8 posts   •   Page 1 of 1