by mckaymmc1 »
Sun Jan 24, 2021 1:03 pm
Hi
If the cables are being adopted by the DNO (Distribution network operation = the local utility company) then they can assist on NERS registration and I believe they all do.
You have stated N power are insisting on this - Npower arent a DNO and dont own any utility infrastructure so not sure why they can insist on anything.
If it is a new build then I would suggest you need to talk to ICPs - Independent connection providers. The NERS register will have a list of those who are registered to work in your area. 30k seems a lot - have you checked and challenged this?