Laying a sharp sand screed as a kitchen floor
Post your questions and get answers regarding all areas of drives, pathways and patios

4 posts   •   Page 1 of 1
Russell Hasleden
Labourer
Labourer
Posts: 2
Joined: Sat Apr 14, 2007 3:07 pm

Laying a sharp sand screed as a kitchen floor

by Russell Hasleden » Sat Apr 14, 2007 3:16 pm

My existing kitchen floor has been removed becaused it was very badly installed. To be able to lay a new screed one end has 75mm the other has 125mm. Can I lay a screed to different levels? Also how long would it be before I can walk and lay a laminate floor down.

Regards

Russell

thedoctor
Posts: 2530
Joined: Sat Apr 08, 2006 1:15 pm

by thedoctor » Sat Apr 14, 2007 6:46 pm

You can lay the screed at different levels Russell but for strength it may be best to put a lightweight aggregate in the mix. Talk to your local builders merchants about lightweight aggregate.

Russell Hasleden
Labourer
Labourer
Posts: 2
Joined: Sat Apr 14, 2007 3:07 pm

by Russell Hasleden » Sat Apr 14, 2007 10:53 pm

Thanks, I know drying times vary, how long would I have to wait before laying laminate on top of the screed.

Regards

Russell

thedoctor
Posts: 2530
Joined: Sat Apr 08, 2006 1:15 pm

by thedoctor » Sun Apr 15, 2007 9:09 am

About 10 days in a normally heated house Russell