hanging drywall/dat and dab
Ask your questions and find answers on many subjects relating to plastering and dry lining

2 posts   •   Page 1 of 1
willi101
Apprentice
Apprentice
Posts: 6
Joined: Mon Feb 25, 2008 6:10 pm

hanging drywall/dat and dab

Post by willi101 » Sun Mar 16, 2008 7:03 pm

when dot and dabing to walls should there be a gap 25mm from the floor level or can the board fit top to bottom floor to ceiling?

kbrownie
Project Manager
Project Manager
Posts: 1995
Joined: Mon Mar 05, 2007 9:36 pm

Post by kbrownie » Thu Mar 20, 2008 12:17 pm

hi
it can rest on floor, but generally you find you need to lift the board a little so a nice tight joint at ceiling. I don't advise you to force board in if cutting a little to big as board will belly out!
Regards
KB

2 posts   •   Page 1 of 1