by kirstenw »
Wed Jan 21, 2009 9:00 am
I have got a penetrating damp problem in my bedroom that is due to be fixed in a week or so. My question is relating to the method the builder intends to use. He plans to remove all of the damaged/damp plaster on Day 1, then fix the problem on the outside of the house, then replaster on Day 2. My concern is that the wall will not be dried out sufficiently, as it took 4 weeks for an internal wall in another area of my house to be dried ready for plastering after flood damage last year. Am I worrying unnecessarily, or am I right to be questioning this?