by sgrahamhyde »
Mon Jun 25, 2007 12:04 pm
I have exactly the same problem except I want to tile my floor, it is currently 125mm below the level of the kitchen floor which I want the finished hight to be, the builders left me some jablite slabs 50mm and some chicken wire, they said to put down the jablite and then cover it with chicken wire before laying a screed of 60mm leaving 15mm for my tiles and tile cement. So several question arrise:
1. Is jablite suitable for this job (This is what they left me so I am kind fo stuck with it)?
2. Will the chicken wire really be sufficient to stop any movement?
3. Will 60mm screed be enough?
4. Should I use just sharp sand and cement in my screed or should I use and agregate with stones or pea beech in?