Plasterer or carpenter first?
Ask your questions and find answers on many subjects relating to plastering and dry lining

3 posts   •   Page 1 of 1
pickup01
Labourer
Labourer
Posts: 2
Joined: Tue Mar 13, 2007 11:34 am

Plasterer or carpenter first?

by pickup01 » Tue Mar 13, 2007 11:38 am

I have a room which needs the old wood work (skirting boards/architraves&doors) replaced and comletely replastering. What's the order of work for this?

thedoctor
Posts: 2530
Joined: Sat Apr 08, 2006 1:15 pm

by thedoctor » Fri Mar 16, 2007 1:39 pm

MANY OF THE ANSWERS TO YOUR POSTS CAN BE FOUND, WITH DIAGRAMS, IN THE DIYDOCTOR PROJECTS SECTION. CLICK HERE www.diydoctor.org.uk/projects.htm

omulcol
Apprentice
Apprentice
Posts: 6
Joined: Wed Mar 28, 2007 7:36 pm

by omulcol » Wed Mar 28, 2007 9:22 pm

Take off all the old woodwork - call in the plasterer - then call the carpenter !

3 posts   •   Page 1 of 1
It is currently Thu Nov 21, 2024 4:56 pm