How long to wait after primer to tile?
Advice and information on tiling and fixing tiles to a variety of surfaces

2 posts   •   Page 1 of 1
Thejohn32
Labourer
Labourer
Posts: 1
Joined: Sat Mar 23, 2013 7:34 am

How long to wait after primer to tile?

by Thejohn32 » Sat Mar 23, 2013 7:41 am

Hi. First post so be gentle.

I am tiling two walls in the bathroom on Monday. One has been re plastered and scored the other is plaster board. I have Mapei Tile Adhesive Primer and will give both surfaces a neat coat. A few questions.

How long do I have to wait before I can start to tile?

Once it is primed is there a time limit I have (in days) before I have to start to tile?

Thank you for any advice.

welsh brickie
Project Manager
Project Manager
Posts: 2610
Joined: Sat Apr 12, 2008 8:54 am

Re: How long to wait after primer to tile?

by welsh brickie » Sat Mar 23, 2013 12:11 pm

24hours usually