hi, have done a 5day courses and purchased a dvd on plastering but they are all telling me different things so maybe you can help me.
1. if skimming over a previous plaster wall how many coats of pva do i use and do i have to wait for it to drybefore applying the skim.
2. do i have to wait for the 1st skim coat to dry before applying the second (final coat) or can i apply it immediately.
3. have practiced a fair bit in my garage, but cannot get the final finish right. For the most part the surface is flat, smooth and glossy but areas appear to have blemishes that i struggle to remove. There is no guidance on the dvd to help me with this problem. The blemish appear as small very shallow shapes (ie as said in previous ) like the various countrys of the world.
My proceedure is as follows
1. pva wall and overskim immediately
2. remove any high points in first skim
3. fill and holes.
4. allow first skim to dry for 20-25mins
5. apply second skim.
6. allow to dry for 20mins.
7. remove high points/ trowel marks using wet trowel and flicking on water
8. paint water to wall, use clean wet trowel to start the smoothing process
9. (at this point my blemishes are appearing) wait 10mins dry trowel 1
10. wait 20mins or so dry trowel 2.
Sorry this long topic but really getting annoyed as cannot see waht im doing wrong.
Darren