Unlevel Shower Tray

by misterdun » Tue Oct 14, 2008 11:23 am

I am installing a non-easy plumb screwfix shower tray onto newly laid 18mm chipboard. There is about a 15mm drop between back to front and was wondering what the best way to level it off would be. I was thinking of packing the lower end but also putting down a layer of cement/sand to strengthen it or is it best to lay a wet mix, if so what would be the best mix to use and do i need to add pva?

TheDoctor4
Project Manager
Project Manager
Posts: 16777203
Joined: Tue Jul 24, 2007 10:12 am
Location: Somerset in the UK in Shepton mallet

by TheDoctor4 » Tue Oct 14, 2008 4:51 pm

Hi

Have you had a look at the DIY Projects area at all: https://www.diydoctor.org.uk/projects.htm There are several projects relating to shower installation and also one forfitting a shower tray that may be usefull: https://www.diydoctor.org.uk/projects/showertray.htm

Regards

misterdun
Apprentice
Apprentice
Posts: 10
Joined: Wed Jul 16, 2008 2:09 pm

by misterdun » Wed Oct 15, 2008 8:00 am

Thanks for the reponse garnico1307, i had laready checked the projects page out and have searched extensively on the web. I can see that i will probably have to put a cement/sand mix but can't find any advice on a mix, should it be a dry mix or fairly runny etc.

bobbych
Apprentice
Apprentice
Posts: 11
Joined: Tue Oct 14, 2008 3:35 pm

by bobbych » Wed Oct 15, 2008 9:34 am

a sand and cement base is the normal way to level it. Dont just pack the low end. the try need to be supported over most of its base or it will flex and break the seal to the screen

chris_on_tour2002
Project Manager
Project Manager
Posts: 1024
Joined: Thu Aug 30, 2007 10:14 pm

by chris_on_tour2002 » Wed Oct 15, 2008 10:13 am

use a wet mix of sand and cement with pva/admix in it as an anti-crumbling agent to help prevent it breaking up.

seal the plywood with pva as well, a 3:1 mix, apply the sand and cement when the pva is still tacky.