Hi everyone, I'm laying a 4" reinforced concrete floor on a dpc membrane.

On top of that I have read I need to put another dpc before I put 4" of floor styrene to which I'm adding water underfloor heating and then a 4" screed to finish off.

My question is how long to let the first four inches dry out before I put the next layer of dpc. I read I need this dpc to protect the polystyrene. If I cover it before it's completely dried right through will I have problems because the moisture is trapped in or will it eventually dry out. Any advise is gratefully received. Thanks

mdpmspitfire
Tradesman
Tradesman
Posts: 36
Joined: Wed Nov 26, 2008 9:32 pm

floor

by mdpmspitfire » Wed Nov 26, 2008 10:17 pm

i would suggest you allow several weeks to allow drying as you are right that the moisture will be trapped. using a dehumifier on a low setting would help but dont dryout too fast. air circulation is best but this time of year and damp air doesnt help
mark

TheDoctor5
Posts: 1381
Joined: Tue Jan 20, 2009 9:17 am

by TheDoctor5 » Fri Jan 30, 2009 9:13 am

If you type the key words of your question into our search box to the left of the site you may find the answer is already posted or is in the DIY projects section of the website. Every post goes through a monitoring process and using the search box may speed up your answer.

3 posts   •   Page 1 of 1
It is currently Sun Dec 22, 2024 2:52 pm